Networks account for most operating earnings
Regulated electricity networks generated roughly two-thirds of SSE's adjusted operating profit. Within that business, SSEN Transmission nearly doubled its investment and doubled adjusted operating profit, which reached £584.0 million from £292.1 million a year earlier.
SSE Renewables recorded adjusted operating profit of £332 million, an increase of about 20%. SSE attributed the gain to higher generation from more favorable weather and new capacity, including Dogger Bank and Yellow River. Lower hedged prices than a year earlier partly offset those gains.
On a reported basis, group operating profit increased to £947 million from £634 million. The interim results, published November 18, 2026, also showed adjusted earnings per share of 66.5 pence, up 83% from 36.3 pence and in line with expectations.
SSE declared a 2026/27 interim dividend of 22.9 pence per share, compared with 21.4 pence a year earlier. Consistent with its stated dividend approach, the payment equals one-third of the previous year's full-year dividend.
Funding the £33 billion investment plan
The first-half spending forms part of SSE's five-year, £33 billion investment plan through 2029/30. The plan represents a tripling of investment over the period, allocating about 80%, or £27 billion, to regulated electricity networks. The remaining 20%, or £6 billion, is earmarked for selective investment in renewables and system flexibility projects.
Chief Executive Martin Pibworth said the plan unveiled a year earlier was "translating into infrastructure on the ground, supporting lower bills and providing greater energy security." He added: "Deliver lasting value for customers and we can deliver lasting value for shareholders too. That's the straightforward equation behind our investment plan."
Adjusted net debt and hybrid capital stood at £11.4 billion on September 30, an increase of £1.3 billion. SSE said faster capital investment was the main reason for the rise, with operating cash flows providing a partial offset.
For the full 2026/27 financial year, the company still expects adjusted investment and capital expenditure to exceed £5 billion. It also expects net debt to remain comfortably within the parameters supporting its strong investment-grade credit ratings.
Transmission and offshore wind construction
Construction is now underway on all 11 of SSE's major transmission projects. At the Dogger Bank offshore wind farm, turbine installation is more than halfway complete: an estimated 150 turbines have been installed across the project, and 100 have been commissioned.
SSE expects Dogger Bank A's 1.2 GW of capacity to be substantially available by the end of the first quarter of 2027. The remaining capacity is expected to become available during final commissioning by the end of the third quarter. Dogger Bank B is expected to be substantially available in the first half of 2027.
The company is also working toward a final investment decision on the 1.4 GW Berwick Bank B offshore wind project in the second half of 2027. It has signed preferred supplier agreements and locked in about 60% of the total expected debt financing at swap rates below 5%.
Earnings guidance unchanged
With November's weather conditions and the key winter months still ahead, SSE retained its adjusted earnings-per-share guidance of 168-193 pence for fiscal 2026/27. Its 2029/30 target also remains unchanged at 225-250 pence.